A Comprehensive Guide to Basement Construction Under Existing London Homes: Process, Challenges, and Best Practices

In London, where space is at a premium, basement construction has become an attractive option for homeowners looking to expand their living space. Whether it’s creating a home gym, cinema room, wine cellar, or additional bedrooms, basements offer a valuable solution. However, constructing a basement under an existing house is a complex engineering challenge that requires careful planning, experienced professionals, and a strong understanding of structural integrity, waterproofing, and site conditions.

At Masters, we have extensive experience in home extensions and renovations, along with strong academic and experiential knowledge of building and construction processes.
This guide will take you through the key aspects of basement construction under existing properties, explaining the process and considerations involved.
Understanding the Feasibility of a Basement

Before any basement construction begins, a thorough site investigation is required. This includes:
  • Soil and ground conditions – Understanding soil composition is crucial for designing foundations and waterproofing systems. London’s clay-heavy soil can pose challenges, such as ground movement and water retention.
  • Existing structure and foundations – The type and condition of the house’s existing foundation will determine the best method for basement excavation.
  • Water table levels – High groundwater levels can complicate excavation and waterproofing.
  • Legal and planning permissions – Some London boroughs have strict regulations on basement construction, particularly in conservation areas.
At Masters, we work closely with the client's architect and engineers. If needed, we can recommend highly experienced architects, structural and temporary works engineers, and Geotechnical Soil Surveyors. We will in our turn come and survey the site to evaluate access, site location, and once everything is clear, will evaluate the work.
Basement Construction Techniques

There are two primary methods for constructing a basement under an existing building: underpinning and piling.

A. Underpinning
Underpinning is a structural reinforcement technique used to deepen an existing foundation, allowing for basement construction beneath a home. This process is particularly suitable for terraced and semi-detached houses where space is limited, and excavation must be carefully managed to maintain structural integrity.
Types of Underpinning:
  • Mass Concrete Underpinning – This traditional method involves excavating sections beneath the foundation in a sequential manner and filling them with concrete. To resist lateral soil pressure, a reinforced concrete (RC) retaining wall is constructed adjacent to the underpinning.
  • Reinforced Concrete (RC) Underpinning – Incorporates steel reinforcement within the concrete, enhancing both vertical and horizontal load-bearing capabilities.
  • Multi-stage Underpinning – Used for deeper basement construction, this technique involves excavating in phases with reinforced supports to minimize ground movement.
Underpinning Process:
  1. Site Investigation – The existing foundation, soil conditions, and structural loads are assessed by engineers before work begins.
  2. Sequential Excavation – Small, controlled sections of the foundation are dug out one at a time to prevent excessive movement.
  3. Temporary Support and Shoring – Temporary props, beams, or trench sheets are installed to stabilize the structure during excavation. Correct sequencing and removal of these supports are crucial to prevent sudden structural loads from causing damage.
  4. Concrete Placement – Concrete is poured into the excavated sections in stages and allowed to cure. Mass concrete underpinning requires a reinforced retaining wall to handle lateral earth pressure.
  5. Structural Slabs Installation – Structural slabs are poured at key stages to prevent collapse due to lateral forces from the surrounding soil. These slabs provide essential support and stability during excavation and underpinning.
  6. Load Transfer – The weight of the existing structure is gradually redistributed onto the new, deeper foundation.
  7. Top-Down or Bottom-Up Construction – In top-down construction, the top structural slab is installed first, incorporating access hatches to facilitate excavation below. As excavation and underpinning progress, the lower slabs are poured, completing the basement’s structural system. This method helps resist lateral soil pressures and enhances site stability. In contrast, bottom-up construction begins with the lowest slab, followed by intermediate and upper slabs. This approach requires additional lateral temporary supports, as the structure lacks the rigidity provided by a top slab. The choice between these methods depends on site conditions, project constraints, and structural requirements.
  8. Waterproofing – After excavation is finished, waterproofing systems are carefully installed, ensuring that the basement remains dry and protected against groundwater ingress.
Underpinning is ideal for terraced and semi-detached homes where space is limited, and excavation must be done gradually to maintain structural integrity.

B. Piled Retaining Walls
For deeper basements or projects with higher water tables, piling may be necessary. This involves driving reinforced concrete or steel piles into the ground to create a stable retaining wall and to counteract hydrostatic pressure, which can push basement slabs upwards. Piles act as anchors, preventing uplift caused by groundwater forces and ensuring the structural integrity of the basement. This is particularly critical in areas with high water tables, where the buoyancy effect could otherwise lead to structural failure if not properly managed.
Types of Piled Walls:
  • Contiguous Piles – Piles are installed with small gaps, and an internal waterproofing layer is added.
  • Secant Piles – Overlapping piles create a continuous waterproof wall.
  • Steel Sheet Piles – Thin interlocking steel sheets driven into the ground. These piles require large machinery for installation, making them impractical in confined spaces under existing houses. They are mainly used for reinforcing the ground when a basement is being excavated in a garden or an open area where space permits.
Piling is more suitable for large-scale basement projects or where high water pressures need to be managed.
Waterproofing the Basement

Waterproofing is critical in basement construction to prevent water ingress and ensure long-term durability. The British Standard BS 8102:2022 outlines best practices for waterproofing underground structures. There are three main types of waterproofing:
1. Type A (Barrier Protection)
Type A waterproofing relies on a physical barrier applied either externally or internally to prevent water penetration. It is particularly effective where the structure itself is not inherently waterproof.
  • External Barrier Protection: A waterproof membrane, such as bituminous coatings, liquid-applied membranes, or bonded sheet membranes, is applied to the outside of the basement walls and floor. This method is effective in preventing water ingress but requires good site drainage to avoid hydrostatic pressure buildup.
  • Internal Barrier Protection: Where external waterproofing is not possible, an internal tanking system is applied. This can include cementitious waterproof coatings or cavity drain membranes. However, internal tanking systems rely on the structural integrity of the basement walls to resist external water pressure.
  • Drainage Considerations: Type A systems are often paired with a drainage system to alleviate hydrostatic pressure and reduce the risk of failure. In high-water table areas, combining Type A with Type C waterproofing is recommended.
2. Type B (Integral Protection)
Type B waterproofing involves designing the basement structure itself to be watertight. This method relies on water-resistant concrete and construction techniques that minimize weak points where water can infiltrate.
  • Waterproof Concrete: Specially designed concrete mixes with reduced permeability are used to construct the basement walls and floor. These often include water-resistant additives to enhance durability.
  • Joint Sealing: Construction joints, which can be weak points for water ingress, are sealed with hydrophilic strips, water bars, or injectable resins to ensure a fully watertight system.
  • Crack Control: Type B systems require careful structural design to limit movement and prevent cracking. Expansion joints and reinforcement strategies are employed to enhance long-term performance.
3. Type C (Drained Protection)
Type C waterproofing involves managing water ingress rather than completely blocking it. This approach allows for controlled water penetration, which is then collected and drained away.
  • Cavity Drain Membranes (CDM): A dimpled membrane is applied to the internal face of the basement walls and floor, creating a void that channels water to a drainage system.
  • Drainage Channels and Pumps: Water is directed to perimeter drainage channels and collected in a sump, where it is then pumped away using mechanical sump pumps.
  • Maintenance Requirements: Unlike Type A and Type B, Type C systems require ongoing maintenance. Pumps, drainage channels, and inspection points must be checked regularly to prevent blockages and ensure the system functions properly.
Combination Waterproofing Systems
In many cases, a combination of waterproofing methods is necessary to achieve a fully watertight basement. Common approaches include:
  • Type A + Type C: External membranes combined with an internal drainage system for added redundancy.
  • Type B + Type C: Integral waterproofing with a cavity drainage system to manage any potential seepage.
  • Type A + Type B + Type C: A comprehensive system where high water table conditions exist, ensuring multiple layers of protection.
Most London basements use a combination of Type A and Type C systems to ensure a dry and habitable space. At Masters, we work to the specifications of the primary designers and engineers, implementing their plans to achieve effective waterproofing solutions.
Ventilation and Air Management

Proper ventilation is essential in basement construction to prevent condensation, mould growth, and stale air build-up. Since basements are naturally enclosed and often have limited natural airflow, managing humidity levels effectively ensures a comfortable and healthy environment.

Key Ventilation Solutions

Mechanical Ventilation Systems
Mechanical ventilation actively circulates air to remove excess humidity, prevent stale air, and improve overall air quality. These systems are particularly useful in basements with limited natural ventilation.

Heat Recovery Ventilation (HRV) Units – Extracts stale air while introducing fresh air, recovering heat in the process.
Examples:

  • Vent-Axia Sentinel Kinetic – Suitable for basements, with high energy efficiency and built-in humidity sensors.
  • Nuaire MVHR System – Offers quiet operation and efficient air exchange.
  • Energy Recovery Ventilators (ERVs) – Similar to HRVs but also transfer moisture, balancing humidity levels in addition to heat recovery. Examples:
  • Panasonic WhisperComfort ERV – Ideal for maintaining balanced humidity and temperature.
  • Broan ERV120S – Compact and efficient, specifically designed for enclosed spaces like basements.
Extractor Fans – Removes humid air and prevents moisture buildup.
Examples:

  • Manrose 150mm In-Line Fan – Ideal for enclosed basement spaces, suitable for continuous operation.
  • Envirovent Silent 100 Design Extractor Fan– Low noise and efficient humidity control.
  • Positive Input Ventilation (PIV) Systems – Pushes filtered air into the basement, reducing dampness and improving circulation. Examples:
  • Nuaire Drimaster Eco PIV System – Provides filtered fresh air and reduces humidity levels effectively.
Dehumidifiers - help regulate moisture levels, preventing condensation and mould growth. They are particularly beneficial in basements prone to high humidity.

Examples:
  • MeacoDry Arete One 20L/25L – A highly efficient dehumidifier with a built-in HEPA filter to improve air quality.
  • Ebac 3850e Dehumidifier – Specifically designed for UK basements, with a Smart Control feature to adjust humidity automatically.
  • EcoAir DC202 Hybrid Dehumidifier – Combines air purification with dehumidification for enhanced indoor air quality.
4.3 Passive Ventilation Methods - Passive ventilation relies on natural air movement to reduce moisture levels. While less effective in fully enclosed basements, it can be a useful supplementary measure.

Examples:
  • Trickle Vents on Windows – Small adjustable vents built into windows to allow a steady exchange of fresh air.
  • Open Windows and Doors (When Possible) – Encouraging airflow through occasional openings.
Why Proper Ventilation Matters
  • Prevents Mould Growth – Keeping humidity below 60% RH stops condensation and microbial build-up.
  • Protects Finishes and Waterproofing – Reduces long-term moisture damage to walls, floors, and ceilings.
  • Improves Indoor Air Quality – Reduces pollutants and stale air accumulation.
  • Enhances Energy Efficiency – Proper ventilation minimises excess heating costs by reducing dampness.
Structural Considerations and Temporary Works

Temporary works are essential in basement construction, ensuring that the structure remains stable throughout excavation and construction. Without properly designed and implemented temporary works, there is a significant risk of structural failure, ground movement, or collapse.

Types of Temporary Works in Basement Construction
Temporary works in basement construction can be categorised into the following main areas​:

Excavation Support:
  • Individual underpin excavations – Each underpin excavation must be supported with shoring to prevent collapse. Horizontal loads increase with depth, so deeper excavations require more robust shoring.
  • Main site excavation – The entire excavation must be planned carefully to prevent collapse and ground movement. Horizontal propping is required at various levels.
Structural Support:
  • Vertical propping – Ensures the stability of the existing building while excavation is underway.
  • Horizontal propping and waling beams – Prevent inward movement of the walls by counteracting lateral earth pressures.
  • Cross-propping systems – Provide additional lateral support to prevent the walls from moving inwards during bulk excavation.
Equipment and Plant Support:
  • Large equipment, such as piling rigs, concrete pumps, and cranes, require proper temporary support foundations to prevent ground instability.
Excavated Soil Management:
  • The weight of stored excavated soil must be considered, as excessive loads can cause instability or add surcharge pressure to the excavation walls.
Site Facilities:
  • Temporary fencing, hoarding, and welfare facilities must be adequately supported and secured.

Importance of Proper Temporary Works in Excavation

A major cause of structural failures in basement construction is the lack of adequate temporary works. The key risks include​:
  • Inadequate lateral support – If the basement walls are not sufficiently propped, they can move inward due to lateral soil pressure, leading to collapse.
  • Premature removal of temporary supports – If propping is removed before the permanent works have gained sufficient strength, it can lead to structural instability.
  • Uncoordinated installation and removal – Temporary supports must be installed and removed in the correct sequence to prevent sudden structural failures.
  • Lack of proper shoring for underpin excavations – Each underpin must be correctly supported to prevent collapse.
Case Study Example:
A failure in Wandsworth, South London, resulted in the collapse of a building because temporary horizontal propping was not installed during excavation. The lateral pressure from the retained ground caused the basement walls to move inwards, leading to structural failure​.

Temporary Works Design and Implementation
Temporary works must be carefully designed, installed, monitored, and removed according to a structured plan. The key roles involved include:
Temporary Works Engineer (TWE):
  • Designs the temporary works, ensuring structural stability throughout the project.
  • Works closely with the Structural Engineer to integrate temporary and permanent structural elements.
Temporary Works Coordinator (TWC):
  • Oversees the planning, installation, and removal of temporary works.
  • Ensures that all site personnel are briefed on the correct handling of temporary structures​.
Structural Engineer:
  • Provides input on load distribution, ensuring the structural integrity of the permanent works.

Construction Sequences: Bottom-Up vs. Top-Down
The choice of construction sequence affects how temporary works are planned and executed.

Bottom-Up Construction
  • The basement ground slab is constructed first, followed by intermediate slabs from bottom to top.
  • Temporary horizontal propping is installed as excavation progresses.
  • As each slab gains strength, temporary props are removed sequentially.
  • Key Risk: More extensive lateral temporary supports are required as there is no upper slab to provide early stiffness.
Top-Down Construction
  • The upper slabs are built first, with access hatches to allow excavation below.
  • As each slab is completed, excavation continues downwards.
  • The basement ground slab is poured last, completing the structure.
Key Advantage: Provides early structural support, reducing reliance on temporary horizontal propping.

Safe Removal of Temporary Works
Temporary supports should only be removed once the permanent structure has gained adequate strength. The following steps ensure a safe transition:
Concrete Strength Testing:
  • Reinforced concrete requires time to reach full strength. Cube testing is often used to confirm its readiness​.
Gradual Load Transfer:
  • Temporary works should not be removed suddenly. Instead, load transfer should be monitored progressively.
Regular Structural Monitoring:
  • Precision instruments should be used to track movement in the existing structure during the transition from temporary to permanent support.

Properly designed and implemented temporary works are crucial for maintaining stability and safety in basement construction. Close collaboration between the Temporary Works Engineer, Structural Engineer, and on-site teams ensures that excavation and underpinning proceed safely without compromising structural integrity. Ensuring the correct sequencing of excavation, propping, and slab installation is vital to a successful basement construction project.
Managing Construction Impact on Neighbours

Basement excavation in London homes often means working in close proximity to neighbouring properties. Without careful planning, these projects can cause structural movement, noise, vibration, dust, and traffic congestion, leading to disputes and complaints. To minimise disruption, a combination of legal agreements, construction best practices, and considerate execution is essential​.

Party Wall Agreements and Structural Safeguards
The Party Wall Act 1996 provides a legal framework for property owners carrying out work that affects shared or adjacent walls, foundations, or boundary structures. This applies to basement excavations because they can impact the stability of neighbouring buildings.
Key Aspects of the Party Wall Agreement
  • Notification Requirement: The building owner must serve notice to adjoining owners before beginning work.
  • Surveyor Involvement: Adjoining owners have the right to appoint a surveyor and a structural engineer to act on their behalf, and the costs for these professionals are covered by the building owner.
  • Structural Considerations: Engineers must predict settlement and movement caused by excavation and underpinning, ensuring that temporary works prevent excessive ground relaxation​.
  • Liability for Damage: If damage occurs to a neighbouring property, even if non-negligent, the building owner remains fully liable for repairs or compensation.
Steps to Prevent Structural Impact on Neighbours
  • Conducting pre-construction surveys to document the condition of neighbouring properties.
  • Using underpinning and piling techniques designed to minimise settlement and vibration.
  • Implementing movement monitoring systems to detect and address any issues in real-time.

Noise, Vibration, and Dust Control
Construction sites generate significant noise and vibration, particularly from breaking out concrete, cutting steel, and using heavy machinery. To comply with environmental regulations and minimise disruption, the following measures should be adopted:

Noise and Vibration Reduction Strategies
  • Compliance with Working Hours:
Standard working hours in London boroughs:
Monday to Friday: 08:00–17:30
Saturday: 08:00–13:00
Noisy work is usually prohibited on Sundays and bank holidays

  • Use of Silenced Equipment:
Muffled compressors and electric tools instead of air-powered alternatives.
Diamond cutting instead of percussive breakers to reduce noise and dust.

  • Dust Suppression Methods:
Water sprays to reduce airborne dust.
Sealed enclosures around demolition and excavation areas.

  • Vibration Monitoring:
Installing vibration sensors to track ground movement and adjust construction techniques accordingly.
Authorities have the power under Section 60 of the Control of Pollution Act 1974 to restrict noisy operations or impose penalties if excessive disturbance occurs​ASUC basement-guideline….

Traffic and Spoil Removal Planning
Heavy vehicle movements for material deliveries and spoil removal can cause traffic congestion and safety hazards. Proper traffic management is essential for minimising disruption.
Best Practices for Construction Traffic Management
  • Developing a Construction Traffic Management Plan (CTMP)
Required by local councils before work begins.
Specifies vehicle routes, timings, and mitigation measures.
  • Scheduling Deliveries and Spoil Removal at Off-Peak Times
Avoiding school rush hours and refuse collection times.
Coordinating with other local construction projects to prevent conflicts.
  • Minimising On-Street Storage of Materials and Equipment
Storing materials on-site where possible.
Using conveyor systems or grab lorries instead of skips to reduce street obstruction.
  • Appointing Traffic Marshals
Directing vehicles safely.
Ensuring minimal disruption to local road users​ASUC basement-guideline….

Early Communication and Good Neighbour Practices
One of the most effective ways to prevent disputes is to engage with neighbours before construction begins.
Recommended Communication Strategies
  • Providing Advance Notice
Inform neighbours of the start date, project duration, and key construction phases.
  • Hosting Informal Meetings
Answering questions and addressing concerns before work begins.
  • Offering Direct Contact Information
Appointing a site liaison officer to handle complaints and updates.
  • Giving Prior Warning of Noisy or Disruptive Work
Sharing schedules of particularly disruptive activities like piling or concrete breaking.
Early engagement reduces resistance and builds goodwill, helping projects progress smoothly​.

Basement construction will always have some impact on neighbours, but with proper planning, legal compliance, and considerate execution, disruption can be significantly reduced. The Party Wall Act, noise and vibration mitigation, traffic management, and open communication are key factors in maintaining good relations and ensuring smooth project progression.
Planning and Legal Requirements

Before basement construction begins, it’s important to secure planning permission and building regulations approval.
  • Permitted Development vs. Planning Permission – Some basement extensions fall under permitted development, but larger projects require full planning permission.
  • Structural Calculations and Building Control – All designs must comply with UK Building Regulations.
  • Insurance and Guarantees – We offer insurance-backed guarantees for structural integrity and waterproofing.
At Masters, we do not handle planning applications or regulatory approvals. We can advise on the necessary steps to take, their sequence, and who to hire, but we commence work only after all permits have been received.
Thinking of adding a basement to your home? Whether you're planning a new basement or need expert advice on the process, we’re here to help. At Masters, we work closely with architects and engineers to ensure a smooth and high-quality build. Contact us today to discuss your project, and let’s explore the best solutions for your home